Titledefines specific phases and milestones (see Figure 1) in the commissioning of electrical, instrumentation and control systems in the process industry. By way of example, it describes activities following the 'completion-of-erection' milestone of the project and prior to the 'acceptance-of-the-plant' phase by the owner. Such activities need to be adapted for each type of process/plant concerned.
Registration number (WIID)50447
Scopedefines specific phases and milestones (see Figure 1) in the commissioning of electrical, instrumentation and control systems in the process industry. By way of example, it describes activities following the 'completion-of-erection' milestone of the project and prior to the 'acceptance-of-the-plant' phase by the owner. Such activities need to be adapted for each type of process/plant concerned.